SEPTEMBER 5, 2016
Erika Borrego, Chief Operations Officer

CONSTRUCTION UPDATE #1
WORK IN PROGRESS:
- Building pad is complete
- Drill and pour piers – 80% complete (55 of 72 complete)
- Casting beds regraded
- Temp and permanent utility applications in & pre-instal inspection completed
- Kitchen bid selected
- Furniture bid pending
- Racking bid pending
UPCOMING WORK:
- Pier caps
- Casting beds
- Plumbing rough in
- Forming tilt wall panels
Anticipated Completion: Summer 2017