SEPTEMBER 5, 2016
Erika Borrego, Chief Operations Officer

CONSTRUCTION UPDATE #1

WORK IN PROGRESS:

  • Building pad is complete
  • Drill and pour piers – 80% complete (55 of 72 complete)
  • Casting beds regraded
  • Temp and permanent utility applications in & pre-instal inspection completed
  • Kitchen bid selected
  • Furniture bid pending
  • Racking bid pending

UPCOMING WORK:

  • Pier caps
  • Casting beds
  • Plumbing rough in
  • Forming tilt wall panels

Anticipated Completion: Summer 2017