FEBRUARY 7, 2017
Erika Borrego, Chief Operations Officer
CONSTRUCTION UPDATE #7
WORK IN PROGRESS:
- 2nd floor concrete pour completed
- Utility work continued (delayed due to weather)
- CMU working near completion
- Sealants and panel joints poured
- Power washed and primed exterior panels
UPCOMING WORK:
- Road work in progress
- HVAC curb installation
- Wall studs in progress
- Plumbing and electrical rough in continues
- Freezer floor in progress
- Window framing to begin
- Glazing starting
Anticipated Completion: Summer 2017