FEBRUARY 7, 2017
Erika Borrego, Chief Operations Officer

CONSTRUCTION UPDATE #7

WORK IN PROGRESS:

  • 2nd floor concrete pour completed
  • Utility work continued (delayed due to weather)
  • CMU working near completion
  • Sealants and panel joints poured
  • Power washed and primed exterior panels

UPCOMING WORK:

  • Road work in progress
  • HVAC curb installation
  • Wall studs in progress
  • Plumbing and electrical rough in continues
  • Freezer floor in progress
  • Window framing to begin
  • Glazing starting

Anticipated Completion: Summer 2017