NOVEMBER 5, 2016
Erika Borrego, Chief Operations Officer
CONSTRUCTION UPDATE #4
WORK IN PROGRESS:
- 15 Panels have been poured and an additional 18 will be poured this week – all panels will be completed in next two weeks
- Building pad will be poured on Wed – 11/9
- Structural Steel arriving on 11/14
UPCOMING WORK:
- Complete casting beds
- Finish panels
- Plumbing and electrical route in
- Erect walls
- Erect steel
Anticipated Completion: Summer 2017