NOVEMBER 5, 2016
Erika Borrego, Chief Operations Officer

CONSTRUCTION UPDATE #4

WORK IN PROGRESS:

  • 15 Panels have been poured and an additional 18 will be poured this week – all panels will be completed in next two weeks
  • Building pad will be poured on Wed – 11/9
  • Structural Steel arriving on 11/14

UPCOMING WORK:

  • Complete casting beds
  • Finish panels
  • Plumbing and electrical route in
  • Erect walls
  • Erect steel

Anticipated Completion: Summer 2017