DECEMBER 7, 2016
Erika Borrego, Chief Operations Officer
CONSTRUCTION UPDATE #5
WORK IN PROGRESS:
- Building pad has been poured
- Panels have been erected
- Structural steel hasĀ arrived
- Structural steel is being erected
- Utilities have begun
UPCOMING WORK:
- Demo and haul off of casting beds
- Structural steel erection
- Plumbing and electrical rough in
Anticipated Completion: Summer 2017