MARCH 4, 2017
Erika Borrego, Chief Operations Officer

CONSTRUCTION UPDATE #8

WORK IN PROGRESS:

  • Glazing done in most punched openings (windows)
  • Utility works continues on Rosa Parks Dr.
  • Water proofing for stone work completed
  • Plumbing rough in work in restrooms started
  • Metal stud framing per ASI’s ongoing
  • Electrical rough in work happening
  • Roofing at lower level roofs continues
  • Painting for exterior floor of building started
  • Stone work on exterior started

UPCOMING WORK:

  • Site work for concrete flat work
  • Freezer floor to be poured
  • Overhead doors to be installed

Anticipated Completion: Summer 2017