MARCH 4, 2017
Erika Borrego, Chief Operations Officer
CONSTRUCTION UPDATE #8
WORK IN PROGRESS:
- Glazing done in most punched openings (windows)
- Utility works continues on Rosa Parks Dr.
- Water proofing for stone work completed
- Plumbing rough in work in restrooms started
- Metal stud framing per ASI’s ongoing
- Electrical rough in work happening
- Roofing at lower level roofs continues
- Painting for exterior floor of building started
- Stone work on exterior started
UPCOMING WORK:
- Site work for concrete flat work
- Freezer floor to be poured
- Overhead doors to be installed
Anticipated Completion: Summer 2017