MARCH 27, 2017
Erika Borrego, Chief Operations Officer

CONSTRUCTION UPDATE #9

 

WORK IN PROGRESS:

  • Taping and floating
  • Tile work in restrooms
  • Fire sprinkler branch lines

UPCOMING WORK:

  • Dumpster/Trash Compactor Pad
  • Water Tank Concrete
  • Kitchen Tile
  • Site Grading
  • Gate Posts
  • Kitchen Vent Hoods
  • Dishwasher Hoods
  • Aluminum Doors
  • FRP
  • Window Caulking

Anticipated Completion: Summer 2017